Budget Guide

Office Fit-Out Cost in Noida: Per Sq Ft Guide

Every fit-out contractor quotes a per-square-foot rate. Almost none of them tell you what sits outside it. This is what the bands actually buy in Noida and Delhi NCR, and where budgets break.

The short answer

A Category B office fit-out in Noida generally costs between ₹1,000 and ₹6,200 per square foot of carpet area. That range is uselessly wide on its own, which is exactly why per-square-foot rates cause so many arguments. The number only becomes meaningful once you fix three things: your specification level, your cabin ratio, and what the landlord has already given you.

BandPer sq ftWhat it typically buys
Functional₹1,000 – ₹1,800Open-plan led, laminate finishes, standard grid ceiling, vinyl or basic vitrified flooring, modular workstations, minimal joinery, limited acoustic treatment
Mid-segment corporate₹1,800 – ₹3,000Balanced cabins and open plan, glass partitions, better ceiling and lighting design, engineered flooring, branded reception, decent acoustics on meeting rooms, mid-tier furniture
Premium₹3,000 – ₹6,200Leadership floors, veneer and stone joinery, feature ceilings and lighting, high-spec acoustics, AV-integrated boardrooms, imported furniture, full brand build-out

The seven variables that actually move your number

Two 12,000 sq ft floors on the same road can be 40% apart on cost. These are the reasons.

  1. Cabin-to-open-plan ratio. Enclosed rooms need partitions, doors, dedicated HVAC, dedicated lighting circuits and acoustic treatment. Every cabin you add raises the blended rate. This is the single biggest swing factor.
  2. What the landlord handed you. A Cat A floor with ceiling, flooring and primary HVAC already in place is a different starting point from a warm shell. A warm shell can add ₹350 to ₹700 per sq ft before you have designed anything.
  3. HVAC scope. Reusing the existing distribution is cheap. Re-ducting for a new layout, adding fresh air, or adding standalone units for server rooms and boardrooms is not.
  4. Acoustics. A meeting room that is genuinely confidential needs full-height partitions to the slab, insulation, acoustic doors and seals. A meeting room that merely looks enclosed does not. Clients often price the second and expect the first.
  5. Server room, UPS and IT. Precision cooling, dedicated power, raised access flooring, containment and structured cabling are a specialist package that regularly gets left out of a headline rate.
  6. Joinery specification. Laminate, veneer and stone are three different cost universes for the same drawing.
  7. Whether loose furniture is inside the contract. Chairs, workstations and soft seating can be 15% to 30% of a fit-out budget. A quote that excludes them will always look cheaper.

What is usually excluded from a per sq ft quote

This is where budgets break. When you compare two quotes, compare the exclusions before you compare the rates.

The comparison test that works

Ask every shortlisted contractor to quote against one identical scope document listing all of the above as in or out. If a contractor will not do that and insists on their own format, you cannot compare them, and that is usually deliberate.

A worked example: 10,000 sq ft in Noida Sector 62

A mid-segment corporate office, Cat A floor handed over, ten cabins, two meeting rooms, one boardroom, a 60-seat open-plan area, pantry and breakout, small server room.

PackageShare of build cost
Civil, partitions, doors and glazing18% – 24%
False ceiling and flooring12% – 16%
Electrical, lighting and data cabling15% – 20%
HVAC modification8% – 14%
Fire detection and suppression4% – 7%
Joinery and millwork14% – 20%
Painting, finishes and branding5% – 8%
Preliminaries, site management and contingency6% – 10%

Loose furniture sits outside this and is normally quoted as a separate schedule so you can value-engineer it independently. Keeping a 5% contingency against site discoveries in an existing building is realistic rather than pessimistic.

Three ways to reduce cost without making the office look cheap

Value engineering works when it targets what nobody sees, not what everybody sees.

How we handle cost

We issue a line-item BOQ before site work begins and lock the cost against it, with exclusions written down rather than assumed. Variations are priced against the same BOQ rates, so a change mid-project is arithmetic rather than a negotiation.

We have delivered ₹24 crore of commercial fit-out in 2025 and over 8 million sq ft to date, including multi-city rollouts for Unacademy, Physics Wallah and Vedantu, and offices for FedEx across Noida and Ghaziabad.

See how we work as an office fit out company in Noida or ask for a BOQ conversation.

Related reading

Frequently Asked Questions

How much does office interior cost per sq ft in Noida?

Cat B office fit-outs in Noida generally run Rs 1,000 to Rs 1,800 per sq ft for functional specification, Rs 1,800 to Rs 3,000 for mid-segment corporate, and Rs 3,000 to Rs 6,200 for premium. The band you land in is driven mainly by your cabin-to-open-plan ratio, HVAC scope, acoustic requirements and joinery specification rather than by location within NCR.

What is not included in an office fit-out quote?

The common exclusions are loose furniture and task seating, AV and video conferencing hardware, IT active components and servers, HVAC capacity upgrades, fire system tie-ins to the base building, statutory approvals and landlord supervision charges, access control and CCTV, artwork and plants, and GST at 18%. Always compare exclusions between quotes before comparing rates.

How much should I keep as contingency for an office fit-out?

Around 5% of the build cost is realistic for a fit-out in an existing building, where site discoveries behind ceilings and in service shafts are normal. On a warm shell or an older building, 7% to 10% is safer. Contingency is not padding; it is what stops a genuine site discovery from becoming a project stoppage.

Does a warm shell cost more to fit out than a Cat A floor?

Yes, materially. A Cat A floor already has raised flooring or screed, a basic suspended ceiling, primary HVAC distribution, base lighting and fire detection. Starting from a warm shell means you fund all of that yourself, which typically adds Rs 350 to Rs 700 per sq ft before any tenant-specific design is considered.

How can I reduce my office fit-out cost without it looking cheap?

Reduce the number of enclosed cabins rather than downgrading visible finishes, since every cabin carries partitions, a door, an HVAC drop, lighting circuits and acoustic treatment. Standardise cabin, meeting room and workstation sizes so repetition cuts joinery cost and site errors. And reuse serviceable Cat A ceiling grid and lighting where your layout allows, which can save Rs 150 to Rs 300 per sq ft.